How Long Does It Take to Build a Custom Home?

If you’re dreaming of a one-of-a-kind home in Lexington, Newton, or Weston, there’s one question that surfaces before flooring samples and Pinterest boards: How long does it take to build a custom home?

The short answer? It takes about 12 to 18 months. The better answer depends on the property, the design, the permitting process, and most of all, the builder. A new construction timeline depends on so much more than weather and trades. It hinges on how efficiently your team can align vision, financing, and logistics at every juncture.

Honorato Company guides our clients in Greater Boston through every phase of the custom home journey, from early design ideas to the final walkthrough and warranty. Our process is built for people who work remotely, travel frequently, and invest in tailored, long-term living. 

Modern home under construction with workers installing windows and siding by Honorato in Greater Boston

What Impacts the Timeline of a Custom Home Build in Boston?

Size and Complexity of the Design

Are you envisioning a modest 3-bed modern farmhouse or a 7,000-square-foot contemporary with a full spa, smart gym, and rooftop terrace? The custom home construction timeline will expand based on structural complexity, specialty rooms, and finish levels. Additions like wellness rooms or smart wine cellars require specialized trades and coordination.

Site Conditions

We evaluate the physical site first, checking out grade, vegetation, drainage, and access points, to determine how long site prep and excavation will take. A steep lot in Weston may need retaining walls and careful grading. A flat Newton parcel may move faster.

We also identify early logistics: where materials can be staged, how equipment will access the site, and what impact the build might have on local traffic or neighbors. This is part of what makes Honorato’s site visit such a powerful, and often underestimated, step in the process.

Permitting and Regulatory Review

The City of Boston and surrounding towns each have their own zoning overlays, setbacks, and permit processes. We’re deeply familiar with the permitting timelines in places like Brookline, Cambridge, and Lexington. Still, even under ideal conditions, Massachusetts custom home permits take up to 30 days after final plans are submitted.

Delays often come from incomplete submittals or unclear scope, two things we actively prevent by submitting complete, dialed-in plans with all documentation attached.

Client Decision-Making Style

Some of our clients want to be in every showroom. Others prefer a curated digital selection sheet they can approve from Aspen or Paris. We love both types equally. The timeline can flex depending on how involved or decisive you’d like to be. At Honorato, we meet you where you are, but we’re always moving forward.

Modern white kitchen with island seating, stainless appliances, and wood-accented prep counter by Honorato Company

Honorato’s Phase-by-Phase Breakdown of a Custom Home Timeline

Every Honorato home follows a clearly mapped path, but it’s tailored for flexibility so that we're always moving at your pace. Here’s how long it typically takes us to build a custom home in the Greater Boston area, step by step.

Discovery, Site Visit & Ballpark Budget (1–2 weeks)

After you reach out, we schedule a Discovery Call within 1–5 days to understand your goals, style,  investment range, and lifestyle habits. Then comes an on-site walkthrough, where we assess everything from slope and soil to sun orientation and setbacks.

At this stage, we may offer a high-level cost range, not a quote, but a sanity check. “Your project will likely fall between X and Y.” If that range aligns with your expectations, we move forward. If not, we discuss value engineering strategies. This early financial transparency is part of our cost-plus model, helping avoid surprise scope creep later.

Initial Estimate & Scope Refinement (1–2 weeks)

If you're comfortable with the preliminary range, we begin crafting your initial estimate. This includes:

  • Preliminary selections (fixtures, finishes, flooring)

  • Square footage goals

  • Must-haves (e.g., wellness room, RH-inspired kitchen, in-law suite)

  • Plan necessities (site conditions, topography, zoning notes)

We provide detailed, link-backed estimates so you can see exactly what we’re pricing out, down to product lines and appliance tiers.

We follow up promptly (within 24–48 hours) after sending this estimate to help guide next steps.

Final Scope, Selections & Refined Estimate (1–4 weeks)

Some clients move fast and finalize their design vision within a week. Others prefer to tour showrooms, review tile samples, and think through cabinet handles over red wine. We’re happy either way.

At this phase:

  • We finalize scope of work 

  • All trades and vendors are lined up

  • You sign off on selections and refined costs

Because we run a cost-plus contract, you have visibility and flexibility throughout, making it easy to shift finishes or update layouts midstream without getting nickel-and-dimed.

See more detailed cost information here.

Design & Plans (4–6 weeks)

Our architects and designers bring the dream to life with floor plans, elevations, and 3D visuals. This phase overlaps with Selections to save time. We handle all coordination with surveyors, engineers, and zoning boards, ensuring everything is ready for permit submission.

Permitting (Up to 30 days)

Once we've finalized plans and your construction deposit is secured, we file for permits. Every town is different, but we’re dialed in on timelines and nuances from Brookline to Wellesley.

Common permit delays we avoid:

  • Incomplete submissions

  • Unclear site plans

Vague energy compliance reports


Mobilization & Site Work (2–3 weeks)

Within 30–45 days of permitting, we’re breaking ground. That includes:

  • Scheduling subcontractors

  • Ordering long-lead materials

  • Site clearing and excavation

We also install erosion controls, fencing, dumpsters, and utilities staging.

Construction workers building a wood-framed house in Greater Boston

Foundation & Footings (2–4 weeks)

We pour the literal groundwork of your home: footings, slab or basement, drainage systems, and waterproofing. Weather and inspections can influence this phase, especially during New England winters.

Framing & Structural Build-Out (4–8 weeks)

This is the "wow" moment: walls rise, rooms take shape, and your dream starts to look real. We install beams, subfloors, and roofs, all checked and re-checked by local inspectors.

Mechanical, Electrical & Plumbing (MEP) Rough-Ins (2–6 weeks)

This phase brings your house to life behind the walls:

  • HVAC ducting

  • Plumbing systems

  • Electrical wiring and smart tech prep

All are carefully inspected before we insulate.

Insulation & Drywall (2–3 weeks)

We insulate for energy efficiency and comfort, using spec-appropriate materials (spray foam, batt, etc.). Then drywall goes up and your spaces feel real and defined.

Interior & Exterior Finishes (8–12 weeks, often in parallel)

The beauty phase. Expect:

  • Flooring, tile, and millwork

  • Custom cabinetry

  • Lighting, built-ins, and wine walls

  • Exterior roofing, siding, decks, and even landscaping

Our specialty trades shine here. See our gallery for some of our favorite finishing touches.

Final Systems, Punch List & Client Walkthrough (2–3 weeks)

We install appliances and complete final inspections. We caulk, touch-up, adjust, and perfect.

Then comes your detailed walkthrough with the project manager, where you learn how everything works, from HVAC to smart lighting.

Interior view of Greater Boston, MA home remodel with angled ceiling design by Honorato Company

Warranty & Ongoing Support (Ongoing)

This is where Honorato stands apart. We're here for you after your move, whether it’s to handle a warranty call, recommend a landscaper, or start dreaming about your next custom build or addition.

Five Ways to Stay on (or Beat) Schedule with Honorato Company

Our custom home process keeps you moving forward without dragging you into every material meeting or code nuance. Here’s how we keep your timeline tight without cutting corners.

Pre-Construction Planning That’s Actually Useful

A lot of builders treat the early phases as fluff. We don’t. The Discovery Call, Site Visit, Ballpark Estimate, and Scope Definition are engineered to smoke out friction points before you commit.

  • We evaluate physical and regulatory constraints early, ensuring no slope, tree ordinance, or setback surprises.

  • We guide the conversation around “wants vs. must-haves,” helping you prioritize clearly and confidently.

  • By the time you sign our pre-construction agreement, you’ll know exactly what’s realistic, what it costs, and where the time risks are.

Financing That Doesn’t Slow You Down

Many clients come to us ready to build, but frozen by the idea of refinancing their sub-3% mortgage. That’s why we now offer project financing through Enhancify.

  • 60-second, soft-pull application

  • Over 30 lenders compared in one step

  • Options for unsecured loans and HELOCs

We include this as part of your pre-construction conversation, so financing is ready before selections or materials ordering begin. 

Streamlined Selections Without the Showroom Circus

We love design. But that doesn’t mean you need to spend four Saturdays debating faucets. Once we define the budget and vision, our team creates a curated list of finish options, complete with links, photos, and pricing.

Want to visit a tile showroom? We’ll book it. Want to approve your kitchen cabinet line from Nantucket over Aperol spritzes? We’ve got you covered.

This digital-first, concierge-backed selection process compresses weeks of indecision into a few confident clicks. You’ll feel in control, not overwhelmed.

Buildertrend Access = Zero Surprises

From the first deposit to final paint touch-ups, your entire project lives inside Buildertrend, our cloud-based construction management platform.

  • See real-time scheduling updates

  • Message your PM or trade team instantly

  • Track payments, photos, and milestones

  • Get alerts before inspections or deliveries

Cost-Plus Transparency That Cuts Change-Order Drama

Nothing kills a timeline like decision paralysis caused by opaque fixed-price contracts. Our cost-plus contract model gives you two key luxuries.

  1. The freedom to shift gears mid-project (swap that fireplace material, add radiant heat in the bathroom).

  2. Full visibility into labor and material costs, so you know where your money is going and what your options really cost.

Build Your Custom Home With a Trusted Greater Boston Contractor

Honorato Company understands how to bring luxury homes to life in Woburn, Lexington, Brookline, Newton, Weston, and beyond. We combine clear communication, cost-plus transparency, and meticulous project management to keep your custom home moving on your timeline and on your terms.

Contact us today to schedule a consultation to start the conversation that results in your dream home being realized.